St. Johns County unanimously approves data center moratorium (Courtesy of the Jacksonville Daily Record) — The St. Johns County Board of County Commissioners unanimously approved an ordinance Nov. 3 to temporarily pause development approvals for medium-scale and large-scale data center projects, giving officials time to study the facilities’ potential impacts and determine whether additional land-use regulations are needed.

The moratorium covers the acceptance, processing and approval of development applications for those projects. It is scheduled to take effect Nov. 15 and expire Oct. 31, 2027, unless the county adopts permanent regulations or repeals the ordinance sooner.

A September Pew Research Center poll found that 60% of U.S. adults feel uncomfortable with a data center operating in their area, with 54% citing negative impacts on the environment and 50% pointing to rising home energy costs. Public comment at St. Johns County meeting mirror those concerns.

The county’s existing Comprehensive Plan and Land Development Code do not contain specific standards addressing data center development, Deputy County Attorney Kealey West told the commission Oct. 6. The review, she said, will examine issues including electricity demand, water consumption, cooling systems, infrastructure needs, environmental impacts and compatibility with surrounding properties.

The moratorium gives county staff time to evaluate those concerns, develop potential local regulations and review a state-initiated interdisciplinary study addressing data center policy considerations. The study is scheduled for completion in July 2027.

The county also must consider limits imposed by state law when developing new regulations. At an Oct. 6 presentation, West told commissioners that state legislation restricts local governments’ ability to adopt more burdensome or restrictive development regulations.

West said that while the county can establish a temporary moratorium for planning purposes, it cannot impose a permanent ban on data center development.

St. Johns County is the second Northeast Florida county to adopt a data center moratorium. The Nassau County Board of County Commissioners approved its own legislation June 8, imposing a temporary moratorium of up to 12 months on data center applications. 

On Oct. 21, the Nassau County Data Center Fact-Finding Committee released a draft report recommending a framework for regulating data centers, including where they can be built and how their demands on water, electricity and infrastructure should be assessed. The commission is scheduled to vote on the recommendations Jan. 25.